Jun 2, 2026

Staff told the Measure P Subcommittee they will release the RFQ on June 15, hold mandatory and proprietary meetings in July, shortlist firms for interviews in August, and seek a council award in November; evaluation will be best-value (200-point scale) with fee at 20%.

The full story

The Measure P Subcommittee on June 2 heard a detailed procurement schedule for the new San Rafael library and community center, as staff moved the project into the RFQ/RFP phase. Project manager Gary Chub of Griffin Structures said the team plans to publish the RFQ on June 15, hold a mandatory pre-RFQ meeting and one-on-one proprietary meetings with teams July 6–7, receive RFQ responses by July 29 and interview shortlisted teams on Aug. 20.