San Rafael subcommittee lays out RFQ timeline for Measure P library and community center
Jun 2, 2026
Staff told the Measure P Subcommittee they will release the RFQ on June 15, hold mandatory and proprietary meetings in July, shortlist firms for interviews in August, and seek a council award in November; evaluation will be best-value (200-point scale) with fee at 20%.
The full story
The Measure P Subcommittee on June 2 heard a detailed procurement schedule for the new San Rafael library and community center, as staff moved the project into the RFQ/RFP phase. Project manager Gary Chub of Griffin Structures said the team plans to publish the RFQ on June 15, hold a mandatory pre-RFQ meeting and one-on-one proprietary meetings with teams July 6–7, receive RFQ responses by July 29 and interview shortlisted teams on Aug. 20.
Sign up to keep reading.
Your free newsletter brings you what your city council, county, and school board discussed and decided.
Keep reading for free
Create a free account to finish this story and see the video, transcript and key details.
Continue with GoogleContinue with emailAlready have an account? Log in →