Reading committee hears construction progress, approves $800,975 contractor payment
Jun 8, 2026
Jun 8, 2026
Project staff presented a dashboard showing contract values, contingencies and schedule status; the committee approved multiple invoices including J&J requisition #2 for $800,975. Designers reported submittal progress and on-site activity including foundations and underground utilities.
The full story
Project staff presented a one-page dashboard summarizing schedule, contract values and contingencies, then the committee approved a slate of invoices recommended by the OPM and design team.