Reading committee hears construction progress, approves $800,975 contractor payment

Jun 8, 2026

Project staff presented a dashboard showing contract values, contingencies and schedule status; the committee approved multiple invoices including J&J requisition #2 for $800,975. Designers reported submittal progress and on-site activity including foundations and underground utilities.

The full story

Project staff presented a one-page dashboard summarizing schedule, contract values and contingencies, then the committee approved a slate of invoices recommended by the OPM and design team.