Stormwater cleanup needs top $18.8 million; county outlines program for recurring maintenance
Jun 10, 2026
Public works staff told commissioners the county faces roughly $18.8 million in initial stormwater contractual cleaning needs for damage tied to Hurricane Debbie and proposed a recurring maintenance program priced about $2 million annually, with per-linear-foot costs that vary widely by condition.
The full story
A public works presentation on June 10 identified substantial stormwater maintenance needs and a recommended approach to make channels and drainage systems more maintainable. The public works presenter said contractors completed about $7.5 million in contractual maintenance projects over the past 18 months and that a list of additional initial cleanings across tributaries such as Braden River and Gamble Creek is estimated at roughly $18.8 million.