Council directs manager to develop work plan to fix stalled Stonecrop drainage project

Sebastian City Council · June 10, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After a lengthy debate over contractor failure and insurance surety, the Sebastian City Council authorized the city manager to develop a work plan and return a contract to correct deficiencies at the Stonecrop drainage site; the motion passed by roll call.

The Sebastian City Council on June 10 directed the city manager to assemble a detailed work plan and return with a contract to repair deficiencies at the stalled Stonecrop drainage project after the original contractor left the site incomplete.

Councilmember Dodd moved to authorize the city to contract to correct the project’s deficiencies and to have the city manager bring back a contract with a defined work plan and inspection/engineering costs; the motion was seconded and carried on roll call. Mayor Jones, Vice Mayor McPartlin, Councilmember None, Councilmember Matthews and Councilmember Dodd voted in favor.

Council debate focused on technical and legal risks after the original contractor failed to finish the work. Multiple councilmembers and staff said the city must press the surety and outside counsel while not leaving residents exposed if another storm strikes. “This is a 2 and a half million dollar hit on our reserves,” Councilmember Dodd said, urging a clear plan, third‑party inspection and daily project reporting before work proceeds.

City staff and counsel told the council the surety/bond company has had notice and the city’s outside attorney is coordinating next steps; staff also described a contingency backup plan for storm events that could require renting equipment to clear mats that threaten neighborhood drainage.

The council’s action authorizes staff to develop the work plan and to notify the surety and outside counsel that the city intends to move forward, with a contract to be returned to council for final approval. Several councilmembers said the mayor would not sign the agreement until the work plan and answers to outstanding questions were provided.

Next steps: staff will work with the proposed contractor, outside counsel and engineers to produce the work plan and cost estimates and bring a contract back to council for approval.