Dunkirk officials note July 1 critical dig, EPA planning materials and anticipated October construction start

Jun 24, 2024

Superintendent Hackworth said a critical excavation was scheduled for July 1 and the village has received EPA program management materials; a Wessler representative noted construction is anticipated to begin October 1, 2024.

The full story

Superintendent Hackworth told the Board on June 24 that a critical dig was scheduled for July 1 despite earlier requests not to plan work that week. He said Vaughn, an AEP contractor, scheduled the work; Richard Walden of Sheldon Gas will have someone on site to assist if a gas line is struck. Board member Drake volunteered to check on the work that day; Hackworth briefed him on steps to follow if utilities are hit.