The city of Fallon presented four projects to the county road board including a $9 million Brian Road/VMP intersection plan (seeking about $930,000 for design now), West Terra Lane resurfacing (~$1.2M at 50/50), a highway shared-use path (city seeking about $400,000 county funds), and Deer Road reconstruction (phase two) with an 80/20 split proposal.
Get email alerts on the City Infrastructure Requests topic
No spam. Unsubscribe anytime.
Chris Clerks, capital improvements manager for the City of Fallon, presented four county funding requests focused on safety and connectivity.
Brian Road and VMP intersection: Clerks said the full project — including design, utility relocation, right-of-way and construction — is roughly $9 million. Given uncertainties around right-of-way impacts, the city proposed focusing county funds on design now (about $930,000) so the project can be refined and future federal applications (CMAC/STP) will have stronger cost estimates.
West Terra Lane resurfacing: Clerks described a mill-and-fill preservation approach across about 1.6 miles (roughly 4.5 lane-miles) with spot repairs in concrete sections and shoulder work. He estimated the project at about $1.2 million on a 50/50 county/city split and noted the corridor carries heavy truck traffic and industrial users.
Highway and shared-use path: The city proposed building a tabled shared-use path to tie into neighboring municipalities’ networks and greenways, with the county contribution estimated near $400,000 (about 24% of the project) and a TAP federal application in progress.
Deer Road reconstruction phase two: Clerks outlined a longer reconstruction and extension of an existing county-funded phase, describing planned 11-foot travel lanes, enclosed storm drainage and a 10-foot shared-use path on the north side. The city seeks right-of-way and construction support and anticipates an 80/20 funding split on that section.
Clerks said the four projects together comprise roughly $20.45 million in total project costs submitted, with an immediate county ask of about $15 million across multiple items; staff recommended staging funding to support design and right-of-way work to increase competitiveness for federal grants.
Board members asked technical questions about drainage and sequencing; staff and the presenter discussed prioritizing design work now to preserve federal funding opportunities. No final county awards were recorded at the meeting.