City reports progress in blight‑elimination program, demolitions completed in several phases
Summary
City staff told the council the blight‑elimination (dangerous-structures) program reduced the initiative inventory from 77 to 68 properties and increased remediations from 53 to 61 in the quarter; staff outlined remaining CDBG‑funded demolitions and upcoming bids.
Get email alerts on the Blight Remediation topic
No spam. Unsubscribe anytime.
City staff presented a quarterly update on the city’s blight‑elimination program and reported measurable progress in removing dangerous and dilapidated structures.
The presenter said the city’s initiative inventory fell from 77 properties in the first quarter to 68 in the second quarter while the number of remediated properties rose from 53 to 61. Staff explained the program uses two demolition tracks: a city initiative backed by the city’s nuisance ordinance and a voluntary program funded through Community Development Block Grant (CDBG) funds. Staff said CDBG phase one included nine properties and phase two included 10, with phase three being prepared for bidding.
Staff listed specific addresses that have been demolished under the city initiative and CDBG work, including 100 Dixie Drive (units 73–80), 204 West Adam Street, 208 Wilkerson Street, 402 Geneva Highway, 501 West Adam Street and 430 Daleville Avenue. The presenter said one additional property from a prior presentation (143 South Carol) was remediated through the CDBG phase-two work.
Officials told the council they anticipate completing city initiative phase one in July 2026 and that phases two and three should finish soon afterward. For phase four properties (previously declared nuisances), staff said they are in a required 20‑day period before further action and that remediation plans are being developed. Phase five will identify roughly 15 additional structures to be addressed in the next phase.
Staff said the city will put remaining demolition packages out for bid in the next one to two weeks and emphasized continued communication with property owners throughout the abatement process. The presentation closed with staff offering to take council questions.
What happens next: staff will return with bid results and updates on the remaining properties and timelines for the next phases.