Audubon County approves plans and bid documents for LE-8 and DO-18 bridge replacements

Mar 30, 2026

The Board of Supervisors approved a right-of-way purchase agreement and the plans and bid documents for the LE-8 Bridge Replacement Project and approved plans for the DO-18 Bridge Replacement Project; Engineer Mitch Rydl said LE-8 is proposed to finish by November 2026 and the notice to bidders will be published this week.

The full story

The Audubon County Board of Supervisors on March 30 approved right-of-way acquisition for the LE-8 Bridge Replacement Project and approved the plans and bid documents for the LE-8 project. Engineer Mitch Rydl presented the LE-8 plans, discussed utilities in the project area and said the project is proposed to be finished by November 2026. Rydl also said he would submit the notice to bidders to the newspaper for publication this week.