Porter County manager: Rolling Meadow storm-sewer replacement underway; full program to take several years

Jun 8, 2026

The county’s program manager reported that phase one of the Rolling Meadow storm-sewer replacement (P26-024) started in early May, will install a 30-inch concrete storm sewer and a 72-inch manhole, and that the multi-phase program could take five to seven years to complete across the subdivision.

The full story

Porter County’s program manager updated the board on P26-024, the Rolling Meadow subdivision storm-sewer replacement project, saying construction began in early May and phase one will replace undersized pipes with a 30-inch concrete storm sewer and 12-inch laterals in finger streets.