Board authorizes $20,000 contingency for Hub demolition inspections
Summary
Klamath County approved a $20,000 allocation from LATCF funds to cover unexpected change orders and inspectors for the Hub demolition, with a requirement that staff notify the Board immediately if funds are used.
Get email alerts on the Hub Demolition topic
No spam. Unsubscribe anytime.
Klamath County Commissioners on March 10 authorized $20,000 from LATCF funds to cover potential change orders and inspection costs during the Hub demolition, citing unknown quantities of asbestos and concrete that could cause delays and cost overruns.
Terry Wells, Property Manager, described difficulties in managing change orders and inspections given uncertainties such as asbestos and concrete quantities. Jeremy Morris, Public Works Director, recommended retaining a local asbestos inspector to minimize delays and limit additional costs; Morris also noted that county directors have a $10,000 hiring limit for such services.
Commissioner Nichols moved to authorize $20,000 from LATCF funds for property management to cover unexpected demolition costs. Commissioner DeGroot seconded; the Board voted unanimously to approve. The Board requested immediate notification if any of the funds are spent.
The authorization is intended as contingency funding to keep the Hub demolition on schedule while minimizing the risk of delay caused by hazardous-material discoveries; the county did not specify additional funding sources or a project completion date at the meeting.