Anderson Perry reports progress on Cedar Springs Road mitigation and permitting; permits expected within weeks
Summary
Engineer Andy Lindseay (Anderson Perry) told the county court field work, biological delineation and geotechnical testing for the Cedar Springs Road mitigation site are nearly complete and permit submissions are expected in the coming weeks.
Get email alerts on the Transportation Projects topic
No spam. Unsubscribe anytime.
Andy Lindseay of Anderson Perry provided a project update on the Cedar Springs Road mitigation and roadway work. He reported that biologists completed delineation around the proposed mitigation site, cultural-resource probes identified some archaeological sites that appear avoidable, and geotechnical testing returned favorable initial results.
Lindseay said the team has a preliminary mitigation-area layout and nearly finished roadway designs; a no-rise floodplain certification and final flood-risk assessment memo are in preparation and are expected to be filed with county planning within a week to several weeks. He said the project team will meet with County staff (Grant Dwey and county engineer) next week to refine design details and then begin permit submissions.
Lindseay characterized the recent findings as generally favorable and said the project is on track to begin permitting within about a month, subject to final reports and state reviews.