Hebron advances flood-improvement plan after updated modeling, design work with developers
Mar 19, 2025
Mar 19, 2025
Consultants presented an updated flood model and a master plan that incorporates developer projects and a possible overflow channel; the U.S. Army Corps of Engineers found a channel could be feasible and might remove mapped floodplain designation from nearly 50 insured structures. Council discussed next steps, including a CDBG-funded culvert project this summer.
The full story
Village of Hebron officials heard detailed findings March 19 on a multiyear effort to update flood mapping and create a coordinated improvement plan that meshes with planned development in the northern watershed.