River Ridge CDD hears legal, drainage and Pelican Sound panel updates; drainage work to start in weeks

Nov 19, 2024

District counsel reaffirmed his opinion on Corkscrew Road ownership while staff reported Johnson Engineering will inspect roadways; the Seaside & Master Drainage Project is scheduled to begin in two to three weeks and the CDD named representatives to Pelican Sound’s Community Safeguard Panel objectives.

The full story

District Counsel Tony Pires told the board Nov. 19 that his opinion about ownership of Corkscrew Road west of U.S. 41 remains unchanged after retrieving documents reviewed for the matter. Bob Schultz said the Village of Estero has engaged Johnson Engineering to inspect streets and walkways to identify repair needs; PSGRC President Neil Collins reported Town Hall discussions are focusing on the U.S. 41/Corkscrew intersection and the east side of Corkscrew Road, and staff Wilhems confirmed the study will include the west side as well.