County project manager cites water damage, missing pilasters and delayed panels in courthouse renovation
Mar 12, 2026
Mar 12, 2026
Project staff told commissioners the courthouse renovation suffered condensate damage from a defective HVAC start-up last July, leaving swollen wood pilasters and missing acoustical panels; staff expect major chamber repairs to take weeks and some punch-list items within 30 days.
The full story
County project staff updated commissioners on the courthouse renovation, detailing lingering damage and a revised timeline for finishing the commission chambers.