County Reports Paving Progress, Engineering Agreement and Potential $300k–$350k Overrun on State Project
Summary
The county's road director updated commissioners on paving, a $268,000 local engineering agreement for a school-area project, planned bid openings, a waterline relocation complicated by beaver dams, and possible $300,000–$350,000 overruns on an ALDOT project that may require local contributions.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The county's roads director told commissioners the paving crew is working across multiple roads in the south end of the county and that several contract actions and grant-funded projects will be brought forward for approval.
He said the county has received a proposed engineering agreement for about $268,000 in local funds to prepare the Coosa Valley Elementary area project for state bidding and noted bid openings were scheduled the next day for a creek cleanup project and an equipment-storage building at the road department.
The director also described a separate state '8-trip' bridge/road project that has encountered worse-than-expected material and soil conditions, leading contractors to submit change orders to ALDOT; the director estimated potential overruns "probably around $300,350,000 extra on this" (the discussion placed the likely additional cost in the low hundreds of thousands and said the MPO has agreed to participate, but the county would remain responsible for 20% of overruns).
Separately, the county described a waterline relocation on Simpson/Sandy Road complicated by beaver dams that have backed water onto property; staff reported a trap-and-relocate approach and manual removal of dams may be required and cited a contractor estimate during the meeting.
Commissioners said they would review engineering agreements and bring recommendations to the next formal meeting.