Council warned storm‑drain projects could require millions up front; impact‑fee timing flagged as key risk
Jun 18, 2025
Staff and council highlighted a timing mismatch between storm‑drain capital commitments and impact‑fee receipts that could force the city to front roughly $4 million if development approvals outpace fee collections; members asked staff to update impact‑fee studies and consider rate adjustments.
The full story
Tremonton officials told the council that several upcoming storm‑drain projects, while included in the impact‑fee plan, pose a timing risk because impact‑fee revenue is collected per new permit and may lag construction commitments.