Council hears Scribner Street storm-sewer update after engineering omission; Oct. 10 completion targeted
Jul 1, 2025
Jul 1, 2025
City staff reported a revised plan to install multiple catch basins at the Summit/Scribner/Cedar intersection to correct storm-water flow; the state is pursuing the engineer's Errors & Omissions coverage and the city may incur a small cost if insurance does not cover corrections. The official project completion date is Oct. 10, 2025.
The full story
City presenter Johnson told the Spooner City Council on July 1 that revised plans to fix storm-water flow affecting N. Summit Street and the intersection of Hwy K, Summit and Cedar call for multiple new catch basins to collect runoff.