Robinson Engineering says Robbins has replaced 85 lead service lines, program set to end Dec. 31

Oct 24, 2023

Robinson Engineering told the Robbins board the lead service-line replacement program has replaced 85 lines, visited about 300 homes and used roughly $1.5 million; applications are still being accepted but the grant-funded program is scheduled to end Dec. 31.

The full story

Jonathan Flowers of Robinson Engineering presented an update to the Village of Robbins on the village's lead service-line replacement program during the Oct. 24 board meeting. He said the contractor has replaced 85 service lines, visited about 300 homes and expended approximately $1.5 million to date.