Planning Commission approves three plats; routine administrative items advanced
Summary
On July 7 the Fargo Planning Commission approved three subdivision plats (Champions Gate at Prairie Farms 4th, Berg addition, Christiansen 32nd Ave S 4th) as recommended by staff and heard staff updates on the Lost Creek addition and Land Development Code timing.
Get email alerts on the Plat Approvals topic
No spam. Unsubscribe anytime.
The Fargo Planning Commission on July 7 approved three subdivision plats and cleared several routine administrative items.
Champions Gate at Prairie Farms 4th: Donald Kress presented this replat on 31st Street South (no zoning change; SR‑3). Staff explained the property has a history of replats and recommended approval so the owner can combine two lots and construct a single residence; no public testimony was offered and the commission approved the staff recommendation on roll call.
Berg addition: Donald Kress described the Berg addition, an industrial replat near 5th Avenue South and 23rd Street used primarily for truck parking; Burg Trucking will remain on the property. Staff noted a city-requested utility easement to consolidate access to water and sewer utilities and recommended approval; the commission approved the replat.
Christiansen 32nd Avenue South 4th: Luke Morman presented a minor subdivision to replat two lots into three at 3102 and 3150 36th Street South. Staff noted a stormwater pond on site, a conditional overlay that remains in place, and coordination with the electric company to reroute an easement; the commission approved staff's recommendation on roll call.
Staff updates: Nicole (planning staff) reported the Lost Creek addition was approved by the City Commission with conditions and that the plat will not be recorded until a developer agreement and funding policy items are coordinated. Staff is reviewing the Land Development Code line‑by‑line with consultants and expects a public draft and code‑connect events in early to mid‑August with consultant follow‑up visits late August.
All three plats passed on motions accepting staff recommendations; roll‑call votes were recorded for the official record.