River Ridge CDD approves irrigation repairs, drainage update and changes landscape contractor

Nov 19, 2024

The board approved a not-to-exceed $15,000 irrigation change order, heard that the Seaside & Master Drainage Project is expected to start within weeks, and authorized terminating Laz’s Lawn Service and engaging GulfScapes at a proposed $58,500.

The full story

District Engineer Charlie Krebs presented a revised scope for the Seaside & Master Drainage Project and said MRI expects work to begin within two to three weeks. Krebs also presented additional irrigation costs from Irrigation Concepts: $4,002.50 to repair damaged wiring and approximately $1,300 each to raise seven to eight irrigation heads.