Spring Grove council asks staff to draft policy on assessing property owners for watermain project

Jun 16, 2026

City Engineer Tim Hruska told the council that assessing property owners for the planned watermain would require a new policy and would likely delay bidding to about February 2027; council directed staff to work with WHKS on a draft for later review.

The full story

City Engineer Tim Hruska told the Spring Grove City Council that shifting the upcoming watermain project’s cost to adjacent property owners would require a new assessment policy rather than relying on past practice. Hruska said the Main Street highway project had been an exception and that adopting a new approach now would delay bidding until "approximately February of 2027," with construction planned in 2027.