CHRISTUS representatives say central‑plant repairs underway; completion pushed to early December
Jul 14, 2026
A CHRISTUS facilities manager told the court the hospital’s central plant structural project is about 25% complete, engineers found degraded concrete and rebar requiring additional demolition and beam replacement, and the finish date moved roughly three weeks to early December.
The full story
CHRISTUS Health representatives briefed the Bee County Commissioners Court on July 13 about structural repairs to the hospital’s central plant that supplies chilled water and emergency power to the main facility.