Meriwether County awards courthouse remediation to Penco, approves related change orders
Jun 23, 2026
After receiving three bids for third-floor and bell-tower remediation, the board approved Penco not to exceed $167,000 and authorized two change orders totaling $14,210 for column repair and exterior painting; lead abatement will be solicited separately.
The full story
County Administrator John Gorton told the board that staff had solicited three remediation proposals for the courthouse third floor and bell tower after EMC’s assessment identified remediation needs. Trauma Services submitted the lowest monetary bid ($89,926.96) but staff reported the company primarily specializes in biohazard cleanup. ServPro’s estimate was $546,128.18. Penco proposed approximately $136,857.34 for the third floor plus an estimated $25,000–$30,000 for bell-tower work, bringing Penco’s total to about $166,857.34.