Developer presents revised Beacon Estates subdivision plans addressing steep slopes and stormwater

Irondequoit Planning Board · July 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Engineers for Beacon Estates asked the board for subdivision and EPOD approvals for five new lots on Newport Road, citing a tree survey and geotechnical study and proposing sewer/stormwater measures; board members asked for clearer stormwater and EPOD application details before the public hearing.

Mike Ritchie of Costage Engineering presented the Beacon Estates resubmittal, asking the board to approve subdivision and EPOD (woodlot/steep-slope) permits to split three parcels on Newport Road into five single-family lots. Ritchie said the team completed a tree survey and a geotechnical report that "showed that the site itself is not susceptible, if as proposed, houses are built in those areas and you don't direct stormwater runoff back to the slopes." He also said driveway grades were revised so slopes do not exceed 10% and sanitary sewer slopes were reduced to about 5–7% to lower velocities.

Board members pressed for clarity on what approvals are being sought now and what will follow. The chair and staff clarified that the immediate request is for subdivision approval and EPOD review; applicants expect individual lot-level site plans and EPOD permits to follow when house footprints are proposed. A conservation-board member asked for more runoff details and said the conservation board reiterated last year’s concerns about impermeable surfaces and preservation of existing old-growth trees and ferns.

Engineers said two lots can tie directly into the existing storm sewer and that other lots would use infiltration/dry-well approaches and sheet flow to the nearest catch basins; Ritchie said the storm sewer ultimately discharges to the bay and the design aims to avoid increasing peak rates or causing erosion. The applicant reported Sea Breeze Water District’s general acceptance and only routine county review comments. Staff agreed to confirm whether site-plan approval is required for single-family development in EPOD areas and to coordinate with Public Works on sewer extension timing.

The board did not take action at workshop; members asked the applicant to provide more detailed per-lot stormwater and EPOD application materials and to confirm the process for utility extensions so staff can verify compliance before the July 27 public hearing.