Get email alerts on the Roads topic
No spam. Unsubscribe anytime.
County highway updates: Co. Rd. 16 work progresses; other county roads reported complete
Summary
Highway staff reported Phase I of County Road 16 complete and Phase II underway with a change order to Flex Funding forthcoming; County Roads 8, 3, 26 and 2N were reported finished and staffing changes noted.
Get email alerts on the Roads topic
No spam. Unsubscribe anytime.
Jesse Sedler, representing the highway department, updated the board on ongoing county road work and staffing.
Sedler reported that Phase I of County Road 16 is complete; Phase II work is in progress toward Greatbend and Phase III will cover the portion west of the interstate. A change order for Co. Rd. 16 will be submitted to Flex Funding for reimbursement. Rumble strips, seeding and permanent sign work are expected to finish next week.
Sedler also told the board that County Roads 8, 3, 26 and 2N are complete. He noted that Mark Vetter’s last day with the department is that day.
The board took no formal action on highway projects at the meeting; Sedler’s updates were informational. Staff follow‑up on the Flex Funding reimbursement and routine project closeout steps were implied.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.
