SiteLogic presents microgrid feasibility; PacifiCorp constraints push county to a phased, behind‑the‑meter approach

Jul 15, 2026

Consultants told Del Norte supervisors a full community microgrid faces Pacific Power transmission constraints and a multiyear, multihundred-million-dollar remedy; the board was presented a lower‑cost phase‑one plan (~$2.1M) focused on rooftop and carport solar at county facilities and agreed to pursue committee review and funding pathways.

The full story

SiteLogic returned to the Del Norte County Board of Supervisors with a preliminary feasibility study that narrows a proposed community microgrid to a phased, behind‑the‑meter approach after engineers found utility transmission constraints.