TxDOT district outlines multi‑year highway construction plan to ease Laredo congestion

Jul 16, 2026

Denise Garcia of the TxDOT Laredo district walked committee members through a portfolio of projects — Loop 20/IH‑69 ($344M, ~42% complete), SH‑84 (ahead of schedule), SH‑255 (71% complete, hot‑mix surface pending) and staged I‑35 widening and interchange work with lead dates into 2029–2032 — emphasizing right‑of‑way, utility relocation and phased construction.

The full story

Denise Garcia, identified in the meeting as the district director of transportation planning and development for the TxDOT Laredo District, gave an extended status update on congestion‑mitigation projects across the district.