TxDOT district outlines multi‑year highway construction plan to ease Laredo congestion
Jul 16, 2026
Jul 16, 2026
Denise Garcia of the TxDOT Laredo district walked committee members through a portfolio of projects — Loop 20/IH‑69 ($344M, ~42% complete), SH‑84 (ahead of schedule), SH‑255 (71% complete, hot‑mix surface pending) and staged I‑35 widening and interchange work with lead dates into 2029–2032 — emphasizing right‑of‑way, utility relocation and phased construction.
The full story
Denise Garcia, identified in the meeting as the district director of transportation planning and development for the TxDOT Laredo District, gave an extended status update on congestion‑mitigation projects across the district.