Citizen Portal

Get email alerts on the Wastewater Project topic

No spam. Unsubscribe anytime.

Ione council hears wastewater project update; contractor targets June 15 substantial completion

City of Ione City Council · July 1, 2026

Summary

City engineer Dane Maben told the council the wastewater project remains active with roughly five septic-tank installations left; the construction schedule shows substantial completion the week of June 15, 2026, and the council approved related payments and change orders.

Dane Maben, engineer with Anderson Perry & Associates, updated the Ione City Council on the city’s wastewater project, saying contractor crews continue septic-tank installations and surface restoration and that roughly five septic installations remain before the contractor will request substantial completion.

The project schedule on file shows substantial completion during the week of June 15, 2026. Maben said the contractor provided a three-week look-ahead schedule to the engineer and that Swaggart Brothers agreed to pay Anderson Perry’s fee for a contract extension.

Council records show Bruce Johnson Construction (subcontractor) is installing new septic tanks and that Swaggart Brothers, Inc. is performing surface restoration and cleanup. The council approved payment for PMR#19 to Anderson Perry & Associates and Swaggart Brothers as part of routine project invoicing.

City staff also told the council the Department of Environmental Quality agreed to allow goats to graze the project’s drainfield for weed control; a consulting agronomist recommended planting clover and Conservation Reserve Program (CRP) grass seed for ground cover.

Finally, the council approved Change Order No. 13 (interest on late payments) and Change Order No. 14 (contract time extension), both items the council had discussed previously in March 2026. No motion language or dissenting votes were recorded in the minutes beyond the approvals noted in the meeting record.

The council did not set a new substantial-completion date at the meeting; the project team will submit a formal request for substantial completion when the remaining installations and restoration work are finished.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source