New Port Richey wraps AMI meter project under budget, approves clarifier and biosolids contracts
Feb 4, 2025
Feb 4, 2025
Council accepted the AMI project closeout with a $54,240 deductive change order and approved awards for clarifier recoating ($90,000), gearbox replacement (award to Ovivo USA) and biosolids hauling ($84.43/ton), noting Pasco County cost shares on several items.
The full story
The New Port Richey City Council approved closing out the city’s Advanced Metering Infrastructure (AMI) project and confirmed several wastewater maintenance contracts at its Feb. 4 meeting.