Council awards $398,321 contract for North 8th Avenue utility upgrades
Summary
The council authorized a $398,321.39 contract with United Pavement Maintenance for water-main, sewer and storm-drain replacement on North 8th Avenue, approving a total project budget of $488,153.39 with contingencies and appropriations from capital funds.
Get email alerts on the Infrastructure Utilities topic
No spam. Unsubscribe anytime.
Oakdale City Council awarded a construction contract for the North 8th Avenue Utility Improvements project to United Pavement Maintenance after staff presented bids and funding allocations.
The project covers the corridor between East C Street and East D Street adjacent to Gilbert Park and includes replacement of the aging 1947 underground utilities (water main, sewer and storm drain), concrete repairs, pavement improvements and new striping. Bids opened April 23; the low responsive bid was $398,321.39. Staff requested an additional $39,832 for construction engineering and inspection contingency and a $50,000 construction contingency, bringing the total project budget to $488,153.39.
Staff recommended and the council approved appropriations from the water capital replacement fund, the sewer capital replacement fund ($69,195) and Measure L funds ($118,993) to cover portions of the work. The need for the upgrades was emphasized by staff because existing infrastructure has reached the end of its useful life and will overlap with ongoing well work in the same corridor.
Council members asked about schedule coordination with well construction and confirmed the bid line items matched the budget. The contract was approved by roll call, 5-0.
What comes next: Staff will issue a notice to proceed and begin construction coordination with well contractors and utility stakeholders; staff said the work will be scheduled to minimize traffic impacts and to coordinate road restoration after overlapping work is complete.