Meadowlark Renewables seeks six-month extension as landfill RNG project advances permitting and easements
Jul 23, 2026
Jul 23, 2026
Spark Renewables representatives told the Reno County Commission they have submitted an air permit, secured one easement and continue well-field work; they asked the commission to extend conditions precedent by six months to complete permits, easements, title work and financing.
The full story
Norman Herrera of Spark Renewables, speaking for Meadowlark Renewables, briefed the Reno County Commission on July 22 about progress on a project to convert landfill methane into renewable natural gas.