District reports steady construction progress on referendum projects
Summary
Superintendent and staff reported masonry, roofing and foundation progress at State Road and Hogan sites and described upcoming precast deliveries and site work; specific construction milestones and tree/power-line work were noted.
Get email alerts on the Construction Update topic
No spam. Unsubscribe anytime.
District staff gave the board a construction update tied to the 2024 elementary upgrade referendum. At the State Road site staff said masons were finishing block work and crews were preparing to close up the roof; interior trades would follow. At the Hogan site, foundations on the north portion were complete and work on the kitchen and public-facing areas continues; precast panels and electrical coordination were reported as near-term items.
Project staff also described site work including stormwater hookups and plans to remove tangled power lines and some trees on the east side of a street while preserving trees on the west side. No change orders or budget revisions were reported at the meeting; staff invited board questions about construction sequencing and remained available for follow-up.