Council authorizes construction management, software integration and engineering support for plant build
Summary
Council authorized task orders for construction management services, process control software integration and ongoing engineering support to oversee the wastewater plant upgrade; several task orders were approved as not‑to‑exceed amounts.
Get email alerts on the Construction Management topic
No spam. Unsubscribe anytime.
To support the construction phase, council authorized multiple task orders under existing contracts. The council approved a task order with Jacobs Engineering for construction management (task order under existing contract) and a separate task order for process control software integration; it also approved a task order for Ardura (engineer of record) to provide construction‑phase engineering support.
Jason Van Gilder described these as necessary roles for a project of this magnitude: the construction management team will handle daily observation, pay estimates and scheduling; the software integration team will program control logic and user interfaces; and the design engineer will provide technical oversight to ensure the built work conforms to the design. Each task order was approved unanimously; staff said these are time‑and‑materials task orders and the packet includes not‑to‑exceed figures for council review.