Engineer: Phase IV sewer near completion; Route 20 preconstruction set for Nov. 14

Oct 22, 2024

Engineer Ryan Holcomb reported Phase IV sewer line work is complete with two weeks of concrete/sidewalk work remaining and paving to follow; he said a change order will be presented next meeting and that the Route 20 Corridor preconstruction meeting is scheduled for Nov. 14, 2024.

The full story

Engineer Ryan Holcomb briefed the council on multiple public-works projects. "Line work is complete," he reported for the Phase IV sewer project, adding that the contractor has about two weeks of concrete and sidewalk work remaining before paving and that a change order for concrete steps, stored materials and quantity adjustments will be presented at the next meeting.