Board hears update on pump redesign, generator RFPs and permit work for Chimney Hill water system

Mar 15, 2025

The water commission reported that pump design work (Tank 3 to Tank 2), a supply/demand chart to support state allocations, generator RFPs for tank and well sites, and B tank design proposals are underway; pipe bursting is paused pending state comments.

The full story

Steve Boyce presented the water commission update: James Walker and staff have drafted a design for new transfer pumps from Tank 3 to Tank 2 and prepared an updated supply/demand chart that the minutes say "shows the impact of upgrades, which will allow the state to release more water allocations." The board is collecting electrical-work quotes and James Walker is assembling requests for proposals for site generators and B tank design and construction.