Board ratifies $150,786 change order for stormwater projects after heated debate on process

Jan 28, 2025

The Board ratified MRI Construction Change Order Estimate #500 for Phase I and II stormwater projects totaling $150,786.09 amid criticism from Vice Chair Terry Mountford about project overruns and authority to approve change orders without a Special Meeting; the Board directed District Counsel to draft 'ground rules' for future approvals.

The full story

District Engineer Charlie Krebs and PSGRC General Manager Eric Long explained that the Change Order and inlet relocations were field responses to existing conditions; the work followed tours with homeowners and site review. Vice Chair Terry Mountford objected, saying the CDD was already "$300,000+ over budget" on similar projects and criticized approving an additional $150,786.09 without holding a Special Meeting, calling it a "major dysfunction in the CDD’s operating process."

Free newsletter

Sign up to keep reading.

Your free newsletter brings you what your city council, county, and school board discussed and decided.

or
Already have an account? Sign in