Contractor claims and schedule uncertainty cloud I-205 Abernathy update

Apr 20, 2026

Area manager Bridal Francis said the I-205 Abernathy project is showing 70% of contract value expended but faces schedule slippage and contractor claims; Change Order 50 granted ~307 days in Jan 2025 and a pending PCO (PCO 61) seeks roughly 107 more days while staff negotiate claims and recovery schedules.

The full story

Bridal Francis, area manager for the I-205 Abernathy project, told the CIAC the project is actively under construction and that the agency has expended about 70% of the contract value to date. She said the official contract completion date is October 2026 but the contractor's latest projections extend finish to late 2027. "So based on the value of the contract amount, we know that we've already expended 70% of those dollars," Francis said, noting that time extensions affect both schedule perception and accrued costs.