Staff reports: Tenderfoot overlay, Waterview progress, 103 Main encroachment flagged for review

Jul 22, 2026

Town engineer and senior planner updated council on capital projects and development: Tenderfoot overlay and Waterview are progressing, Nordstrom Rack plans an Oct. 1 grand opening, and 103 Main remodel will require an encroachment agreement because plans show doors onto town property.

The full story

Town Engineer Dan Burrows briefed the council on several capital projects and construction schedules. He said concrete and post‑tensioning work is underway on recent projects and that Tenderfoot Street overlay is out to bid with an anticipated contract in August. Dillon Dam Road resurfacing is expected to move forward in the fall with an advertised week‑long closure and roughly 2–3 days of active work.