Engineer reports: Phase II AMD/AML ROWs mostly secured; Chub Run and Phase IV sewer projects delayed awaiting approvals
Oct 28, 2025
Oct 28, 2025
The town's engineer reported ROWs secured for Phase II (28 of 34), an environmental assessment submitted to the Office of Surface Mining (10/23/25) and bid plans targeted by year-end; Chub Run contractor start is likely delayed to year-end and Phase IV awaits PSC and DEP approvals for a Sandy's Hardware connection.
The full story
The engineer provided a written report updating multiple infrastructure projects. For the Phase II AMD/AML project the report states right-of-ways are secured on 28 of 34 parcels and the environmental assessment was submitted to the Office of Surface Mining on Oct. 23, 2025; the town is aiming to put the project out for bid by the end of the year.