Putney Selectboard reviews town hall renovation plan, notes grant spending deadlines
Summary
Town Manager Karen Astley told the Selectboard that preliminary plans and schedules are in place for the Renew Town Hall project and that two restricted grants require spending by mid‑2026 and year‑end 2026; the board directed follow-up actions on construction documents and environmental review.
Get email alerts on the Town Hall Renovation topic
No spam. Unsubscribe anytime.
The Putney Selectboard heard an extended update on the Renew Town Hall project from Town Manager Karen M. Astley, who said the team has met with Vermont Integrated Architects (VIA) and construction manager HP Cummings to review preliminary cost estimates and a draft schedule. Astley noted two grant deadlines the board must meet: "Paul Bruhn funding ($95,000) must be spent by June 30, 2026" and "MERP—this money ($402,500) must be spent by December 31, 2026," and said the MERP funds are targeted for HVAC, front doors and building energy‑envelope improvements.
Astley summarized next steps for the project: VIA is to develop Phase 1 and 2 construction documents (windows/doors/envelope and HVAC), a Phase I environmental assessment is required before window work can proceed, and the team is pursuing additional funding including a potential VCHP ADA Modification Grant (up to $150,000) that could fund a LULA lift and other accessibility work. The memo accompanying the report estimates a 10–12 month construction schedule and divides cost responsibility into three buckets—construction, design and owner costs. The board recorded these timelines and the action items to have VIA deliver construction documents and to explore funding and fundraising options.