Space-frame delay small but fix reduces scope: board hears construction updates
Summary
District staff reported a schedule slip on the indoor space frame with submittals delayed to late July and manufacturing expected in September, but engineers identified 12 columns that can be reinforced with plates rather than full replacement, reducing timeline and cost risk.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
Board members received a construction update on the junior-high/high-school space frame and other building projects. Staff said finalized structural drawings arrived July 8 but DSI submittals were delayed; current projections set manufacturing near the end of September and onsite installation in October, pushing completion back roughly three months.
Engineers reported that rather than replacing the entire column system, 12 columns show weak points and can be strengthened by welding reinforcement plates to the columns. The presenter said that approach “was all the fix that I needed,” and that it is a simpler, faster remedy than an all-new structure. The elementary addition was reported as occupiable after punch-list work and receipt of a certificate of occupancy, with only minor interior finishes remaining.
Board members asked staff to track submittal milestones and to return with an updated schedule and cost impact if the DSI timeline shifts further. No formal vote was required; members reiterated the importance of safety and timely communication with contractors.