Courthouse project progresses; board flags potential out‑of‑contract AV costs

Jul 22, 2026

Project manager reported the courthouse roof and windows installed and drywall underway; commissioners scheduled a meeting on courtroom AV/sound and noted uncertainty whether AV boxes/TVs are covered by contract or will be out‑of‑scope project expenses.

The full story

County project staff reported the courthouse construction is advancing: the roof is complete, windows are installed, drywall and some basement finishes are done, and ductwork and air handlers are being connected. The county has scheduled a security meeting with the sheriff’s office and corrections to define courtroom security and AV placement.