Premier Lakes reported minimal red algae to be treated, remediation of most aeration issues with two units still needing electrical work, recent dry-retention treatments, and a three-week delay on a Zombie box delivery for the Masters due to backorder.

Dustin Hormann of Premier Lakes told the River Ridge board crews ‘‘identified minimal red algae in the lakes, which will be treated tomorrow,’’ and that dry-retention areas were recently treated. He said aeration issues had been corrected except for two units that need electrical work scheduled for the following Monday or Tuesday.

Mr. Hormann also reported that a ‘‘Zombie box’’ ordered for the Masters is on back order and expected to be installed in three weeks. Eric Long asked District Engineer Charlie Krebs to inspect littorals behind 20859 Glen Eagles Lakes Drive and obtain costs to replant Cord Grass and Arrowhead.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source