Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Lake Maintenance topic

No spam. Unsubscribe anytime.

Vendor reports minimal red algae, aeration fixes and delayed equipment delivery

River Ridge Community Development District Board of Supervisors · January 28, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Premier Lakes reported minimal red algae to be treated, remediation of most aeration issues with two units still needing electrical work, recent dry-retention treatments, and a three-week delay on a Zombie box delivery for the Masters due to backorder.

Dustin Hormann of Premier Lakes told the River Ridge board crews ‘‘identified minimal red algae in the lakes, which will be treated tomorrow,’’ and that dry-retention areas were recently treated. He said aeration issues had been corrected except for two units that need electrical work scheduled for the following Monday or Tuesday.

Mr. Hormann also reported that a ‘‘Zombie box’’ ordered for the Masters is on back order and expected to be installed in three weeks. Eric Long asked District Engineer Charlie Krebs to inspect littorals behind 20859 Glen Eagles Lakes Drive and obtain costs to replant Cord Grass and Arrowhead.