Vendor reports minimal red algae, aeration fixes and delayed equipment delivery
Jan 28, 2025
Premier Lakes reported minimal red algae to be treated, remediation of most aeration issues with two units still needing electrical work, recent dry-retention treatments, and a three-week delay on a Zombie box delivery for the Masters due to backorder.
The full story
Dustin Hormann of Premier Lakes told the River Ridge board crews ‘‘identified minimal red algae in the lakes, which will be treated tomorrow,’’ and that dry-retention areas were recently treated. He said aeration issues had been corrected except for two units that need electrical work scheduled for the following Monday or Tuesday.