TxDOT official reports schedule changes for Uniroyal and Loop 20 work; I‑35 lanes to be expanded
Jul 23, 2026
A TxDOT-area engineer told the committee the contractor had aimed for September–October completion of a Char project but now expects work into early next year; Uniroyal improvements will expand I‑35 main lanes to three lanes each way and Loop 20 traffic switches may be delayed as contractors propose precast bridge elements to speed construction.
The full story
In response to a question from S1, S3 (an agency official) provided status updates on several regional roadway projects. S3 said a contractor had earlier indicated an intention to complete a Char project by September–October, but that schedule now looks more like the beginning of next year. S3 also said contractors are on board for remaining direct connectors at I‑35 and I‑69 and that letting for Uniroyal improvements is occurring after prior utility conflicts were resolved.