Developers outline multi-year timeline, traffic and access plans for reclamation solar site

Jul 22, 2026

Project representative presented a phased construction schedule for the reclamation solar site with pile installation, module work and electrical testing stretching into 2027, estimated peak workforce of 300–350 and 750–1,000 truck deliveries; commissioners pressed for emergency access and road-mud mitigation plans.

The full story

Travis Bruce Ord, representing the solar contractor, gave a detailed schedule and said mobilization began July 7. He described major phases: site preparation now, pile installation and foundations from September to March, tracker and module installs October 2026–April 2027, electrical work through August 2027, and site restoration into early 2028.