Floodplain elevation and new FEMA rules shape Bandon auditorium approval

Mar 11, 2025

Discussion over a 0.8-foot difference in base flood elevation (15.2 vs 16 feet) and the city’s timing relative to new FEMA/state rules was central to the hearing; the applicant agreed to use 16 feet and elevate the building one foot above base flood elevation.

The full story

A technical question about base flood elevation (BFE) was a central part of the hearing. The applicant's representative discussed a discrepancy between survey data (15.2 feet) and the adopted FIRM number of 16 feet and said the team can work with staff to meet whichever elevation the city requires for this application.