Town Administrator Trish Waugh told the Selectboard the Upper Lincoln Gap Road work is complete under a $41,875 grant requiring a 20% match ($8,375); the town has spent $29,397.90 so far and expects remaining labor and equipment charges to bring costs close to the full grant budget.

The full story

Town Administrator Trish Waugh told the Selectboard on May 5 that work on Upper Lincoln Gap Road has been completed under a grant award of $41,875 that requires a 20% local match of $8,375. "To date, the Town of Lincoln has incurred $29,397.90 in expenses, and it is anticipated that the remaining material, equipment, and labor costs will bring the total project cost close to the full grant budget," Waugh said in the meeting minutes.