Keystone board sets fall 2026 completion target for sewer upsize and authorizes bid advertisement

Jan 21, 2026

Trustees set the sanitary sewer upsize construction completion date for fall 2026 and authorized advertising the sewer line upsize project for bid. Public Works reported the sewer plant blowers require new seals and can be repaired in-house.

The full story

The Keystone Board of Trustees on Jan. 21 set the sanitary sewer upsize construction completion date for fall 2026 and authorized staff to advertise the sewer line upsize project for bid. Trustee David Cofoid moved the schedule and Trustee Matthew Fullilove seconded; the motions passed unanimously.